Price base — August 2026

Construction material and works prices in Cameroon

The base every quote line is compared against. Douala and Yaoundé, August 2026 edition, in FCFA. Low and high band: a price inside the band is normal, above it is worth discussing.

30 items, updated August 2026.

→ On a phone, scroll the table to the right for Yaoundé and the source.

Construction material and works prices in Cameroon — August 2026
ItemUnitDoualaYaoundéSource
Cement 50 kgsac4 700 – 5 2004 800 – 5 400material price survey
Hollow block 10u120 – 150130 – 160material price survey
Hollow block 15u150 – 185160 – 200material price survey
Hollow block 20u200 – 240210 – 260material price survey
River sandm39 000 – 14 00011 000 – 16 000real quotes collected
Gravel 5/15m314 000 – 18 00015 000 – 20 000real quotes collected
Gravel 15/25m313 000 – 17 00014 000 – 19 000real quotes collected
Gravel, size unspecifiedm313 000 – 18 00014 000 – 20 000real quotes collected
Rebar HA8kg820 – 950850 – 980material price survey
Rebar HA12kg800 – 930830 – 960material price survey
Rebar, diameter unspecifiedkg800 – 950830 – 980material price survey
Binding wirekg900 – 1 200950 – 1 300material price survey
Nailskg800 – 1 100850 – 1 200material price survey
Formwork timberm345 000 – 55 00048 000 – 60 000real quotes collected
Timber batten 8x8ml700 – 1 000750 – 1 100real quotes collected
Roof lathml400 – 650430 – 700real quotes collected
Clay pot 15u350 – 450380 – 480material price survey
Reinforced concrete 350m395 000 – 125 000100 000 – 135 000mercuriale and unit price schedules
Clay-pot slab, laidm216 000 – 23 00017 000 – 25 000mercuriale and unit price schedules
Clay pots, supply per m2m22 800 – 4 2003 000 – 4 600material price survey
Blockwork 15, laidm26 500 – 9 0007 000 – 9 500mercuriale and unit price schedules
Cement renderm22 200 – 3 2002 400 – 3 500mercuriale and unit price schedules
Floor tiling 40x40, laidm28 000 – 13 0008 500 – 14 000real quotes collected
Aluminium roof sheet 6/10m26 500 – 9 5007 000 – 10 000material price survey
Interior paint, 2 coatsm21 500 – 2 5001 600 – 2 700mercuriale and unit price schedules
Metal dooru45 000 – 85 00048 000 – 90 000real quotes collected
Sliding aluminium windowm235 000 – 55 00038 000 – 60 000real quotes collected
PVC pipe 110ml2 500 – 4 0002 700 – 4 300material price survey
Cable 2x2.5 mm2ml550 – 850600 – 900material price survey
Material haulagem33 000 – 6 0003 500 – 7 000real quotes collected

FCFA per stated unit — FCFA, August 2026

Your quote, against this base

Drop it in. The verdict is free: you see how many lines are concerned and the estimated total gap before paying anything.

drop a quote

How this base is built

Three sources, cited row by row. The State mercuriale and unit price schedules for works; real quotes collected in Cameroon for what tradespeople actually charge; a supplier price survey in Douala and Yaoundé for materials. The base is dated and republished monthly: a 2024 concrete price is useless in 2026.

Labour

Structural labour billed as a lump sum normally represents 18 to 30 % of the materials subtotal. Above that, the line is worth discussing. A “sundries and contingency” line rarely exceeds 5 % of the quote total.

Other cities

Bafoussam, Bamenda and Garoua are priced off the Yaoundé base; Kribi off Douala. We say so rather than invent a survey we did not run.

What this base does not tell you

A band is not a fair price for your site. Distance, site access, finish quality and a material's brand all legitimately move a price. A gap is a fact; what it means is for you and the tradesperson to discuss. That is why every report ends with a negotiation message, not an accusation.